Percent Complete Columns of the Activity Table (2024)

Activity % Complete field

The percent of the activity that has been completed.

The calculation is based on the formula for the selected Percent Complete Type. The Percent Complete Type can be Units, Duration, Physical, or Scope.

If the selected activity's percent complete type is Duration, the percent complete is calculated as (Planned Duration minus Remaining Duration) divided by Planned Duration.

If the activity's percent complete type is Units, the percent complete is calculated as (Actual Labor Units plus Actual Nonlabor Units) divided by (Actual Labor Units plus Actual Nonlabor Units plus Remaining Labor Units plus Remaining Nonlabor Units).

If the activity's percent complete type is Physical, either the user records the percent complete manually or the field is set to calculate using steps. To calculate using steps, the Calculate Activity % Complete from activity steps option must be set in Project Preferences.

If the activity's percent complete type is Scope, the percent complete is calculated by Oracle Primavera Cloud and cannot be modified in P6.

BL Project % Complete Type field

The % complete type of the activity in the project baseline.

BL Project Activity % Complete field

The activity % complete of the activity in the project baseline.

BL Project Cost % Complete field

The cost % complete of the activity in the project baseline.

BL Project Duration % Complete field

The duration % complete of the activity in the project baseline.

BL Project Units % Complete field

The units % complete of the activity in the project baseline.

BL1 % Complete Type field

The % complete type of the activity in the primary baseline.

BL1 Activity % Complete field

The activity % complete of the activity in the primary baseline.

BL1 Cost % Complete field

The cost % complete of the activity in the primary baseline.

BL1 Duration % Complete field

The duration % complete of the activity in the primary baseline.

BL1 Units % Complete field

The units % complete of the activity in the primary baseline.

Cost % Complete field

The percent complete of costs for all labor resources, nonlabor resources, and expenses for the activity.

Calculated as Actual Total Cost divided by At Completion Total Cost multiplied by 100.

Cost % of Planned field

The percent complete of planned costs for all labor resources, nonlabor resources, and expenses for the activity.

Calculated as Actual Total Cost divided by BL Planned Total Cost multiplied by 100. The value can exceed 100. The baseline total cost is the activity's at completion cost from the current baseline.

Duration % Complete field

The duration percent complete for the activity or WBS.

Calculated as Planned Duration minus Remaining Duration divided by Planned Duration multiplied by 100. The value is always between 0 and 100. P6 always calculates Duration % Complete from the Planned Duration and Remaining Duration, even if you enter Duration % Complete manually. For example, if an activity has an Planned Duration of 25.57h and you enter 90% for Duration % Complete P6 will calculate the Remaining Duration as 2.55h and will correct the Duration % Complete to 90.03%.

Duration % of Planned field

The actual duration percent of planned duration for the activity.

The baseline duration is the activity's at completion duration from the project baseline.

Calculated as Actual Duration divided by BL Duration multiplied by 100. The value can exceed 100.

Expense Cost % Complete field

The percent complete of cost for all expenses associated with the activity or WBS.

Calculated as Actual Expense Cost divided by At Completion Expense Cost multiplied by 100. Always in the range 0 to 100.

Labor Cost % Complete field

The percent complete of costs for all labor resources assigned to the activity or WBS.

Calculated as Actual Labor Cost divided by At Completion Labor Cost multiplied by 100. Always in the range 0 to 100.

Labor Units % Complete field

The percent complete of units for all labor resources for the activity or WBS.

Calculated as Actual Labor Units divided by At Completion Labor Units multiplied by 100. Always in the range 0 to 100.

Material Cost % Complete field

The percent complete of costs for all material resources assigned to the activity or WBS.

Calculated as Actual Material Cost divided by At Complete Material Cost multiplied by 100. Always in the range 0 to 100.

Nonlabor Cost % Complete field

The percent complete of costs for all nonlabor resources assigned to the activity or WBS.

Calculated as Actual Nonlabor Cost divided by At Completion Nonlabor Cost multiplied by 100. Always in the range 0 to 100.

Nonlabor Units % Complete field

The percent complete of units for all nonlabor resources for the activity, WBS, or project.

Calculated as Actual Nonlabor Units divided by At Completion Nonlabor Units multiplied by 100. Always in the range 0 to 100.

Percent Complete Type list

Determines the way in which the application calculates the percent complete for the activity.

This default activity percent complete type will be applied to all new activities added to a project. If you change this setting for an existing project that has activities, the percent complete type of those existing activities will not be changed.

Performance % Complete field

The percentage of the activity planned work that is currently complete.

Performance % Complete is used to calculate earned value. It can be based on the activity percent complete, on the 0/100 rule, on the 50/50 rule, depending on the technique for computing earned-value percent complete for the activity's WBS.

Physical % Complete field

The activity percent complete, which is either user-entered or calculated from activity steps.

To calculate Physical % Complete from activity steps, the Calculate Activity % Complete from activity steps option must be enabled for the project.

Schedule % Complete field

The activity schedule percent complete, which specifies how much of the activity's project baseline duration is complete so far.

Calculated based on where the current data date falls relative to the activity's project baseline start and finish dates.

If the data date is earlier than the baseline start, the schedule percent complete is 0. If the data date is later than the baseline finish, the schedule percent complete is 100. The schedule percent complete indicates how much of the activity duration should currently be complete, relative to the selected project baseline.

Scope % Complete field

The percent complete for the activity if the percent complete type is set to scope. Scope is calculated in Oracle Primavera Cloud when P6 is integrated with Oracle Primavera Cloud for scope management.

Units % Complete field

The percent complete of units for all labor and nonlabor resources assigned to the activity.

The percent complete is always in the range 0 to 100.

Calculated as Actual Units divided by At Completion Units multiplied by 100.

Percent Complete Columns of the Activity Table (2024)

References

Top Articles
3-Ingredient Cranberry Sauce Recipe
59 Heirloom Recipes from Grandparents
Canya 7 Drawer Dresser
Ets Lake Fork Fishing Report
Kraziithegreat
Gabriel Kuhn Y Daniel Perry Video
Pitt Authorized User
Www.megaredrewards.com
Oppenheimer & Co. Inc. Buys Shares of 798,472 AST SpaceMobile, Inc. (NASDAQ:ASTS)
Revitalising marine ecosystems: D-Shape’s innovative 3D-printed reef restoration solution - StartmeupHK
Erin Kate Dolan Twitter
Hope Swinimer Net Worth
1Win - инновационное онлайн-казино и букмекерская контора
General Info for Parents
Studentvue Columbia Heights
Lesson 8 Skills Practice Solve Two-Step Inequalities Answer Key
Byte Delta Dental
The Ultimate Guide to Extras Casting: Everything You Need to Know - MyCastingFile
Busted News Bowie County
Two Babies One Fox Full Comic Pdf
Knock At The Cabin Showtimes Near Alamo Drafthouse Raleigh
Jcp Meevo Com
Strange World Showtimes Near Savoy 16
Criterion Dryer Review
Vera Bradley Factory Outlet Sunbury Products
WPoS's Content - Page 34
Jail Roster Independence Ks
Shoe Station Store Locator
Craigslist/Phx
The Menu Showtimes Near Amc Classic Pekin 14
Kattis-Solutions
Chattanooga Booking Report
Frostbite Blaster
Clark County Ky Busted Newspaper
Waffle House Gift Card Cvs
Sephora Planet Hollywood
Myql Loan Login
Weather Underground Bonita Springs
Review: T-Mobile's Unlimited 4G voor Thuis | Consumentenbond
Danielle Ranslow Obituary
511Pa
Arcane Bloodline Pathfinder
Best GoMovies Alternatives
Skyward Cahokia
Tyco Forums
Amateur Lesbian Spanking
Wzzm Weather Forecast
Food and Water Safety During Power Outages and Floods
Hy-Vee, Inc. hiring Market Grille Express Assistant Department Manager in New Hope, MN | LinkedIn
Koniec veľkorysých plánov. Prestížna LEAF Academy mení adresu, masívny kampus nepostaví
Https://Eaxcis.allstate.com
Primary Care in Nashville & Southern KY | Tristar Medical Group
Latest Posts
Article information

Author: Barbera Armstrong

Last Updated:

Views: 5721

Rating: 4.9 / 5 (79 voted)

Reviews: 86% of readers found this page helpful

Author information

Name: Barbera Armstrong

Birthday: 1992-09-12

Address: Suite 993 99852 Daugherty Causeway, Ritchiehaven, VT 49630

Phone: +5026838435397

Job: National Engineer

Hobby: Listening to music, Board games, Photography, Ice skating, LARPing, Kite flying, Rugby

Introduction: My name is Barbera Armstrong, I am a lovely, delightful, cooperative, funny, enchanting, vivacious, tender person who loves writing and wants to share my knowledge and understanding with you.